The steel plates and flaggers on Agoura Road between Lindero Canyon Road and Lakeview Canyon Road are posted as Pure Water Project work. The project's own weekly notice calls the job "urgent pipeline repair and installation." The urgent part is older than Pure Water. It's a drinking-water main under the Lindero Canyon intersection that has failed repeatedly since 2023. The new recycled-water pipes are being installed at the same time to keep the disruption shorter.
That pairing explains why work started this fall and why it should last months, not the better part of a year. It also explains why the full westbound closure discussed this summer is not part of the current plan.
The Main That Kept Breaking
On May 5, 2026, a leak opened on a 24-inch steel potable-water main at Agoura Road and Lindero Canyon Road. The Las Virgenes-Triunfo Joint Powers Authority's August 10, 2026 board packet says crews repaired it right away and staff then recommended moving up the line's replacement.
That leak was not the first failure at this intersection. The same packet describes several main breaks there in July and August 2023. It also says replacement was already planned because the pipe's coating had deteriorated. The May break damaged the roadway and disrupted traffic. Westlake Village's July 2026 engineering department report uses the same framing. It calls the summer's work "expedited potable water line replacement work, which is associated with the emergency pipeline break."
So the work is urgent because of a pipe that already carries drinking water to homes and businesses on this side of the city, whatever the Pure Water signs say.
Why the Pure Water Pipes Are Going In at the Same Time
The August packet describes one combined job. Two Las Virgenes Municipal Water District potable lines are being relocated. In the same work, the JPA is extending its recycled-water pipeline and adding a reverse-osmosis-concentrate line. The packet estimates about $3.5 million for all of the intersection work.
Combining the work shortens the disruption. Conejo Valley View reported that at the July 8 City Council study session, LVMWD projected total construction impacts of about five months with the two jobs combined, down from 10 to 11 months if done separately.
The new lines are part of a much larger system. The city's July 8 study session report explains that the Pure Water Project takes surplus recycled water from the Tapia Water Reclamation Facility. That water has already been filtered and disinfected. It goes to a new Advanced Water Purification Facility on Agoura Road in Agoura Hills for membrane filtration, reverse osmosis, and ultraviolet light with advanced oxidation. From there it goes to Las Virgenes Reservoir, where it is blended with imported Northern California water and treated again at the Westlake Filtration Plant before delivery.
The same report traces where the pipes will run. One route follows Agoura Road from Lindero Canyon Road. Another runs along Lindero Canyon Road toward Triunfo Canyon Road, and a third climbs the Pentachaeta Trail to the reservoir above the Three Springs neighborhood. The Agoura Road segment from Lindero Canyon west into Thousand Oaks was scheduled to begin in August 2026. The remaining lines are scheduled for 2027.
The project is large, and the corridor is only one piece of it. LVMWD's September 18, 2026 announcement puts the overall budget at $466 million. Financing includes $84 million in State Water Board loans and grants and a $251 million EPA WIFIA loan, and the stated goal is operation by 2030. Citing a Thousand Oaks project summary, Conejo Valley View reported that the finished system will supply up to 30 percent of the area's drinking water. LVMWD currently relies entirely on imported water.
How the Road Got Here, Week by Week
The weekly updates on the Pure Water site show months of preparation before any asphalt came up:
- July 9, 2026. Potholing for the water line replacement began, according to the city's July engineering report.
- Week of August 17. Potholing continued between Lindero Canyon and Lakeview Canyon to prepare for the urgent repair.
- September 4. Potholing on the corridor wrapped up, followed by a pause.
- Week of September 28. No construction or lane closures were scheduled. The repair phase was set to start October 5.
- October 5 and 7. Asphalt removal and steel plates went in October 5, and pipeline installation began October 7, starting near Knightsgate Road and working west.
- Week of October 26. Crews were installing pipe near Greengate Court and moving west.
The excavation start slipped several times in September, from mid-September to the end of the month and then to October 5. Every weekly notice carries the same caveat that weather and field conditions can move the dates. Read the four-to-six-month estimate the same way.
The Westbound Closure That Came Off the Plan
The plan presented to the City Council on July 8 included a much bigger disruption than drivers have seen so far. The study session report said westbound Agoura Road west of Lindero Canyon would close to through traffic for about six weeks. Drivers would have been detoured via Lindero Canyon Road and Lakeview Canyon Road, with the emergency intersection work timed to overlap.
The same report listed three businesses on this stretch as stakeholders that raised "significant concerns" about the closure: the Westlake Inn, The Stonehaus and the Chevron station. According to Conejo Valley View, Westlake Village Inn CEO Chris Culty told the council a westbound closure would affect customer access, deliveries and operations. He said he supported more night work if it shortened the closure. Village Chevron, at 31505 Agoura Road, also sent the council a written comment about construction impacts.
The city's July engineering report records what happened at the session:
"The council provided comments and feedback to LVMWD focused on minimizing impacts on the community and local businesses and specifically requested that the District eliminate the proposed westbound Agoura Road closure from the traffic handling plans."
The current plan follows that request. The latest posted update covers phased work with temporary lane closures, traffic shifts, turn restrictions, parking restrictions and flagging. It does not list any full westbound closure, and it says access to nearby homes and businesses will be maintained whenever possible. The six-week detour in the July study session report and in some early-October coverage is no longer the plan on the record.
The same session took up construction hours. The report noted that the council had earlier told staff not to allow nighttime construction on Agoura Road because of neighborhood noise. It also said the council would be asked to consider limited night work, and possibly some 24-hour phases, at the Lindero Canyon intersection to shorten traffic impacts. The October 28 council agenda has no item approving night work. The October 19 weekly update mentions both daytime and nighttime work over the course of the project but lists weekday hours as the regular schedule.
What the Posted Schedule Says for the Drive
Here is the most recent update, for the week of October 26, 2026, at a glance:
| Item | What the update says |
|---|---|
| Location | Agoura Road between Lindero Canyon Road and Lakeview Canyon Road |
| Active area | Near Greengate Court, moving west |
| Work | Asphalt removal, excavation, pipeline installation and repairs, underground equipment, temporary roadway restoration |
| Hours | Monday through Friday, about 7 a.m. to 4 p.m., varying by activity and location |
| Traffic | Temporary lane closures, shifts, turn and parking restrictions, flagging; expect delays |
| Duration | About four to six months |
Counting from the October 5 start, four to six months puts the end of the corridor work somewhere between early February and early April 2027, if the schedule holds. The posted updates do not yet give a date for the work inside the Agoura Road and Lindero Canyon Road intersection itself. That is the spot where the old main failed and where the city expected the hardest traffic impacts.
Residents headed to the Westlake Village Inn, The Stonehaus or Village Chevron will be driving through an active work zone for most of the winter. All three remain on Agoura Road along the work corridor, and the posted plan is to keep driveways reachable as crews move west. The Project Outreach Team takes questions at (818) 245-4440. The Westlake Village construction page posts each week's update and offers email signups for Westlake Village, Agoura Hills and Thousand Oaks.
Infrastructure work like this affects which routes neighbors take, when a listing photographs well, and how easily buyers can reach a showing on a given weekday. Owners along the Agoura Road corridor who are planning a move this winter or spring are welcome to talk through timing with Tina Lucarelli. Request a private consultation and complimentary home valuation, and Tina will plan your listing around the posted construction schedule.